A loud thud was heard yesterday across Ontario at 11 a.m. It was the dropping and the introduction of the Ottawa Light Rail Transit Commission report. It was a 650-plus-page document detailing the problems we’ve had with our LRT system. It’s something I have fought for in this place—thanks to residents and community members back home, who I want to thank for their work.

Sometimes, the truth hurts, and it certainly hurts this morning for advocates of public-private partnerships in infrastructure, because Justice William Hourigan, who led this report, said the following: “The P3 model caused or contributed to several of the ongoing difficulties on the project ... the city traditionally had a hands-on leading role in projects, given the lesser role it played under this mode, the city was left in a position where it had limited insight or control over the project.”

P3s are an accident waiting to happen. They will not offer the transparency the public deserves. That is the lesson, I believe, from Ottawa’s LRT failure.

But right now, as I speak, the same P3 consultants and contractors who made a mess out of Ottawa’s LRT are building the Eglinton Crosstown.

I call on this government to read Justice Hourigan’s report, to learn the lessons, to not waste the public money, and to make sure the mess that happened in Ottawa never happens again.